4
$\begingroup$

I am curious as to how different is precast concrete design than conventional cast-in situ reinforced concrete design as far as structural engineering is concerned.

To my mind, they should be the same, because precast is essentially using the same materials as cast-in situ, with the same material characteristics. The only difference between them is just one is casted in batch in a factory, and another is casted on site.

Am I right? What does Euro Code or ACI say about it?

$\endgroup$
6
  • $\begingroup$ Pre-cast has to be designed to withstand transporting and lifting loads - also perhaps provided with specially designed lifting points... $\endgroup$
    – Solar Mike
    Commented Feb 4, 2020 at 10:32
  • $\begingroup$ So if anything, precast has to undergo more stringent cjvrcks than normal concrete design ? $\endgroup$
    – Graviton
    Commented Feb 4, 2020 at 10:45
  • $\begingroup$ So if anything they have to be designed to meet all the loads that they will encounter... $\endgroup$
    – Solar Mike
    Commented Feb 4, 2020 at 11:38
  • $\begingroup$ @SolarMike any structural code of practice reference on this, such as Euro code or ACI code ? $\endgroup$
    – Graviton
    Commented Feb 4, 2020 at 11:43
  • $\begingroup$ You can read the codes - I don't feel the need. $\endgroup$
    – Solar Mike
    Commented Feb 4, 2020 at 11:47

2 Answers 2

2
$\begingroup$

Fundamentally the design principles are the same - the concrete doesn't much 'care' if it is cast in its final location or somewhere else then moved when it has cured.

In Eurocode (specifically EN1992-1-1, ‘Eurocode 2: Design of concrete structures- Part 1-1: General rules and rules for buildings’) there is a section ‘Additional rules for precast concrete elements and structures’ which has supplementary rules. That is, the majority of the design is the same, but you get some additional rules to follow. The additional rules cover transient situations, temporary and permanent bearings and the detailing of connections and joints between members.

The transient rules are mainly because in a precast yard the manufacturer wants to strike elements quickly – well before they reach their final strength, so you’ll be lifting and shifting elements when the concrete is only partly cured. The code doesn’t actually have specific rules to follow, it just says that transient conditions should be “considered specifically” (clause 10.2, referring to 10.1.1)

The connections and joints parts do have some specific rules to tell you how to handles such matters as making a slab by joining individual planks, i.e. how you quantify the behaviour of typical connections between the planks. The codes has rules about treating half-joints, types of bearings, anchorage of reinforcement at support and so on.

Overall, section 10 is nine pages out of 230 in the code, so relatively little and minor additional material.

$\endgroup$
2
$\begingroup$

The connections of precast concrete requires more specialized design and also more specialized installation crew in the field. The joints in precast concrete construction are the most critical items. Poorly designed or installed joints can lead to progressive collapse. Also the temporary loads during construction can be critical for the design and installation sequence of precast concrete.

$\endgroup$

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.