Jun 30, 2016 at 9:52 | vote | accept | Murat Dal | ||
Jun 27, 2016 at 16:36 | comment | added | Wasabi | Paying later reduces the NPV of the payment for them. Also, it may very well be a simple matter of "hey, I need to show my bosses the results for the 28-day results, regardless of what the 7-day tests say. So yeah, wait until you do the 28-days to get paid." | |
Jun 27, 2016 at 16:00 | history | answered | AndyT | CC BY-SA 3.0 |